PANAJI: Three proposed iron ore dump recovery projects in Sanguem will have to undergo further documentation before moving ahead, after the Goa State Expert Appraisal Committee (SEAC) raised concerns over gaps in the environmental assessments submitted by the companies.
The committee, at its 301st meeting held on October 30, decided against taking the proposals forward until the project proponents provide more detailed information on the possible environmental consequences of the proposed operations.
The projects involve three existing iron ore dumps in Costi and Dudal villages. Dump No. 1 covers 25.80 hectares across Costi and Dudal, while Dump Nos. 3 and 4 occupy 1.15 hectares and 3.80 hectares respectively in Costi.
Goa Sponge and Power Ltd had submitted the proposal for Dump No. 1, while Sarus Infrastructures Pvt Ltd had moved the proposals concerning the other two dumps.
During the scrutiny, SEAC found that the submitted Environmental Impact Assessment (EIA) documents did not provide sufficient information for a comprehensive examination of the projects.
The companies have now been asked to revisit their environmental reports and provide a more detailed assessment of the proposed activities, including their potential impact on areas within a 10-km radius of the sites. The revised submissions must also spell out measures to minimise or address the identified environmental risks.
All three applications have been placed under the Additional Details Sought (ADS) category, leaving their further consideration dependent on the submission of the required information.
In a separate decision, the committee recommended environmental clearance for the proposed scientific handling of an iron ore dump at Bandoli village in Dharbandora.
The project, proposed by KAI International Pvt Ltd, covers 19.01 hectares and has been recommended for clearance subject to the prescribed general and specific conditions.