The official of Public Work Department visited the Atal Setu bridge and its approaches today.
During the visit it was noticed that the surface varying hotmix coat is laid over the concrete coat and due to dislodging of localised bonding the potholes were developed at few locations.
The contractor viz., M/s L&T has already been intimated to rectify the same on priority basis by GSIDC.
As per the contract conditions as there is a Defect Liability Period, the contractor viz., M/s L&T has to attend and carry out rectification/repair works at their own cost during the Defect Liability Period and no cost is incurred by GSIDC/ Government.