New Delhi: The Supreme Court has expressed serious concern over the worsening pollution in the Yamuna river, observing that despite enormous amounts of public money being spent on cleaning it, the river has continued to become more polluted.
The court said the condition of the Yamuna and its 520 drains exposed major failures in civic administration across the towns, cities and villages situated along its banks, where untreated wastewater continues to enter the river.
During a hearing on a petition concerning the river’s restoration, the court highlighted several shortcomings in the existing Yamuna Action Plan and questioned the effectiveness of measures taken by authorities.
In its November 4 order, the Supreme Court pointed out contradictions in the action plan regarding encroachments in Delhi’s O-Zone, the protected floodplain of the Yamuna. While the plan claimed that water bodies and wetlands in the zone were free from encroachment, an annexure identified all 35 listed water bodies and wetlands as encroached.
The court called for protecting the O-Zone as a green area and extending its boundaries upstream and downstream wherever feasible. It also stressed that permanent constructions should not be permitted, apart from green parks and essential public infrastructure, allowing the river sufficient space to follow its natural course.
The court further revealed that none of Delhi’s 37 Sewage Treatment Plants (STPs) meet the standards prescribed by the Central Pollution Control Board. Only five comply with the required bacteriological limits.
Emphasising that the Yamuna is one continuous ecosystem flowing through multiple states and Union Territories, the court said its protection must be treated as a shared responsibility rather than an isolated state-level issue.
To establish accountability, the court proposed penalties wherever water quality deteriorates while passing through or exiting a state, Union Territory or district. The CPCB has been directed to prepare a compensation formula, allowing authorities to recover penalties from polluters and negligent officials.
The court also ordered all STPs, Common Effluent Treatment Plants and government-operated biogas plants to install tamper-proof smart energy meters and continuous inflow and outflow monitoring systems within one month.
All operational and water quality readings must be uploaded live on CPCB and State Pollution Control Board websites. Data interruptions exceeding 24 hours will be presumed to indicate that a facility is not operating unless the operator establishes otherwise.
Additionally, the CPCB must conduct quarterly surprise inspections of major treatment plants. Environmental compensation will be imposed for every day of non-compliance.
The court has also directed states and central ministries to appoint senior nodal officers within two weeks. Officials responsible for treatment plants and major drains must be publicly identified and submit monthly progress reports directly to the Supreme Court.